Majestic Star Casino & Parking Garage
-
Pittsburgh, Pennsylvania
The Bottom Line: HJ Foundation installs over 1,700 piles, at the height of winter, with very difficult site conditions, ahead of schedule and with zero safety incidents at this landmark casino in Pittsburgh.
Challenging Weather & Site Conditions:
HJ Foundation, in a partnership with Case Foundation, both Keller Companies, worked together with Keating/Smoot Construction JV to install more than 1,700 piles during February and March in Pittsburgh under very challenging weather and site conditions. The JV was very pleased to receive the deep foundations ahead of schedule.
Schedule & Safety:
HJ Foundation and Case Foundation are proud to report that even while operating under very challenging weather and site conditions, and while saving weeks on the schedule, safety was never compromised – zero safety incidents occurred.
Services Provided:
-
1,700+ augered piles
-
18-inch diameter (200-ton & 165-ton compression piles)
Scope of Work:
-
Production pile installation
-
All grout
-
Furnish & install pile rebar
-
Stockpile on site all spoils for disposal
-
Perform pile layout & as-built survey
-
Shooting all grades

Firms Involved on the Project:
-
Owner: PITG Gaming, LLC
-
Contractor: Keating/Smoot Construction, A Joint Venture
-
Engineer of Record: The Harman Group
-
Geotechnical Engineer: Civil & Environmental Consultants, Inc.
Contact HJ Foundation
U.S. HEADQUARTERS
| Phone: | (866) 751-4545 |
| Fax: | (305) 592-7881 |
| Address: | 8275 NW 80th Street Miami, FL 33166 |
| Email: | info@hjfoundation.com |
| Offices: | Tampa, Fort Myers, Atlanta, Chicago |
Projects
6000 Indian Creek
The building’s unique location on the Intracoastal Waterway creates spectacular views for residents, but also presented a series of challenges for HJ.
Projects
Hotel Victor
The Hotel Victor is located mere inches away from the historic Versace Mansion on Miami Beach’s Ocean Drive.
Projects
Our Lady of Lourdes Replacement Hospital - Lafayette, Louisiana

Our ease of contracting and ability to perform quality work in a highly productive and safe manner allowed our client to save 3 weeks on schedule...